Client Spotlight: Christ The Center Ministries

Projects Completed: Ground-up construction of Nursery School, Primary School, Chapel/Main Hall

Project Duration: 13 Months (Design and Build)

Project Year: 2023 – 2024

Work Undertaken:  General Construction (Structural works, cosmetic work, electrical and mechanical engineering were all done by Crux Engineering)

Crux Engineering & Construction Limited has performed all of CTCM’s work as it has developed as an organization over the last 5 years. We have designed and built their Nursery, Primary and Secondary school campuses to completion.

 

  • The buildings are all based on agreemental standard (code). This is a compressed brick (interlocking) bricks system, the bricks are called hydro foam blocks, One of the most robust engineering structures used with a compressive strength varying between 6.5 mpa upto 9 mpa depending on the material source.
  • Used on storeyed structure, earthquake and weather resistant